Tuesday, September 29, 2009

Update Summary of Key Restoration Projects

The following is an update summary of some of the key projects going at Island Towers:
1. Installation of new 3" water main pipe: The actual installation is complete, and all our water is now being supplied by the new pipes. We are currently in the process scheduling the asphalt, concrete, and landscape contractors to come in and fix the damage from the installation of the new pipe.
2. Reworking the walkways, stairwells and balconies: the walkways and stairwell are finished, except for touch up work. On Oct 2, 09, Steve Carpenter and Jodie Canon will start inspecting the balconies. They will enter as many apartments as possible and survey each balcony for actual damage. A second date, to survey the balance, has not been identified yet.
3. Installation of hard wired smoke detectors: McGee, the electrical contractor, just notified us that the city granted us the permits to do the work. He would like to start next week. We'll have to coordinate with the Board, because at least one Board Member, or committee member will have to be present when McGee enters each apartment.
4. Cleaning the outside of the windows: started yesterday and should finish today or tomorrow.