West Tower Walkway Warranty Work, Building Restoration Project

Island Towers Association, Inc.
Building Restoration Project
West Tower Walkway Warranty Work

Please remain off the walkways during the times posted. Re-work is costly and time consuming. Stairwell work will be completed during down times. Respect all cordened off areas.

Deck Coating Schedule West Tower

Tuesday, September 8th: All floors pressure washed. Be aware of workers’ locations, they may not see you. No floor closures necessary.

Wednesday, September 9th: All floors cut in with primer - where vertical and horizontal surfaces meet. No floor closures necessary. Keep your distance from wet areas.

Thursday, September 10th: Sealant rolled onto flat surface, floors closed as follows:
· 8th floor: 9:00am – 1:00pm
· 7th floor: 10:00am – 2:00pm
· 6th floor: 11:00am – 3:00pm
· 5th floor: 1:00pm – 5:00pm

Friday, September 11th: Sealant rolled onto flat surface, floor closed as follows:
· 4th floor: 9:00am – 1:00pm
· 3rd floor: 10:00am – 2:00pm
· 2nd floor: 11:00am – 3:00pm
· 1st floor: 1:00pm – 5:00pm

Monday, September 14th: All floors cut in with color coat – where vertical surface meets horizontal surface. No floor closures necessary. Keep your distance from wet areas.

Tuesday, September 15th: Color coat rolled on flat surface, floors closed as follows:
· 8th floor: 9:00am – 1:00pm
· 7th floor: 10:00am – 2:00pm
· 6th floor: 11:00am – 3:00pm
· 5th floor: 1:00pm – 5:00pm

Wednesday, September 16th: Color coat rolled onto flat surface, floors closed as follows:
· 4th floor: 9:00am – 1:00pm
· 3rd floor: 10:00am – 2:00pm
· 2nd floor: 11:00am – 3:00pm
· 1st floor: 1:00pm – 5:00pm


Thursday, September 17th: Spatter coat and top coat applied to flat surface, floors closed as follows:
· 8th floor: 9:00am – 4:00pm
· 7th floor: 9:00am – 4:00pm

Friday, September 18th : Spatter coat and top coat applied to flat surface, floors closed as follows:
· 6th floor: 9:00am – 4:00pm
· 5th floor: 9:00pm – 4:00pm

Monday, September 21st: Spatter coat and top coat applied to flat surface, floors closed as follows:
· 4th floor: 9:00am – 4:00pm
· 3rd floor: 9:00am – 4:00pm

Tuesday, September 22nd: Spatter coat and top coat applied to flat surface, floors closed as follows:
· 2nd floor: 9:00am – 4:00pm
· 1st floor: 9:00am – 4:00pm

Jodie Canon (102E)