Work Schedule for the re-coating of the walkway/stairwells.

Island Towers Association, Inc.
Building Restoration Project
Update
August 8, 2009


We have been waiting awhile to have our walkways re-coated. We now have a schedule that is posted below. We will begin the the East Tower. 2 weeks will be needed to complete all floors and walkways. Weather delays are possible – if there are changes in the schedule a posted announcement will be placed on the bulletin board in the lobby. Please remain off the walkways during the times posted. Re-work is costly and time consuming. Stairwell work will be completed during down times. Respect all cordoned off areas.

Work begins at 9:00am. West Tower’s schedule will be posted shortly. A lot of the re-coating will be done on selected areas and floor closing may not be necessary.

Deck Coating Schedule East Tower

Monday, August 24th: All floors pressure washed. Be aware of workers’ locations, they may not see you. No floor closures necessary.

Tuesday, August 25th: All floors cut in with primer - where vertical and horizontal surfaces meet. No floor closures necessary. Keep your distance from wet areas.

Wednesday, August 26th: Sealant rolled onto flat surface, floors closed as follows:
· 8th floor: 9:00am – 1:00pm
· 7th floor: 10:00am – 2:00pm
· 6th floor: 11:00am – 3:00pm
· 5th floor: 1:00pm – 5:00pm

Thursday, August 27th: Sealant rolled onto flat surface, floor closed as follows:
· 4th floor: 9:00am – 1:00pm
· 3rf floor: 10:00am – 2:00pm
· 6nd floor: 11:00am – 3:00pm




Friday, August 28th: All floors cut in with color coat – where vertical surface meets horizontal surface. No floor closures necessary. Keep your distance from wet areas.

Monday, August 31st: Color coat rolled on flat surface, floors closed as follows:
· 8th floor: 9:00am – 1:00pm
· 7th floor: 10:00am – 2:00pm
· 6th floor: 11:00am – 3:00pm
· 5th floor: 1:00pm – 5:00pm

Tuesday, September 1st: Color coat rolled onto flat surface, floors closed as follows:
· 4th floor: 9:00am – 1:00pm
· 3rf floor: 10:00am – 2:00pm
· 2nd floor: 11:00am – 3:00pm


Wednesday, September 2nd: Spatter coat and top coat applied to flat surface, floors closed as follows:
· 8th floor: 9:00am – 4:00pm
· 7th floor: 9:00am – 4:00pm

Thursday, September 3rd: Spatter coat and top coat applied to flat surface, floors closed as follows:
· 6th floor: 9:00am – 4:00pm
· 5th floor: 9:00pm – 4:00pm

Friday, September 4th: Spatter coat and top coat applied to flat surface, floors closed as follows:
· 4th floor: 9:00am – 4:00pm
· 3rd floor: 9:00am – 4:00pm
· 2nd floor: 9:00am – 4:00pm



1st floor will not need a complete re-do. Areas needing attention will be touched up and cordoned off. No floor closure will be necessary.